Enbridge declines to estimate Line 3 startup despite positive state ruling

CALGARY — The CEO of Enbridge Inc. says an updated environmental review released by a Minnesota state agency on Monday is a “good outcome” but declined to speculate on when its oft-delayed Line 3 pipeline replacement project will be completed.

The state Department of Commerce found no serious threat to Lake Superior if crude oil leaks from the pipeline that carries Canadian crude from Alberta across North Dakota and Minnesota on the way to Enbridge’s terminal in Superior, Wis.

State regulators ordered the update after the Minnesota Court of Appeals in June declared that an earlier review, issued in February 2018, was inadequate because it failed to specifically address the potential impacts of a spill into the Lake Superior watershed.

CEO Al Monaco, speaking on a webcast from Enbridge’s New York investor day on Tuesday, said the Minnesota Public Utilities Board will allow comment on three topics — adequacy of the final environmental impact statement, the certificate of need and the routing permit — at a one-day oral hearing on Dec. 19, with the comment period closing in mid-January.

“We think it’s a good outcome that the PUC is going to have a comment period related to all three of those items,” he said.

“It doesn’t change our approach in that we’re not providing any specific guidance on in-service date but obviously a good, positive outcome here, I think.”

The project would double the capacity of the existing Line 3 pipeline, which was built in the 1960s and is increasingly subject to cracking and corrosion. Environmental and tribal groups have been fighting the project because of the potential for spills in the Mississippi River headwaters region and because the oil would contribute to climate change.

The Canadian portion of the pipeline entered service on Dec. 1. Analysts at Stifel FirstEnergy say they are estimating a Jan. 1, 2022 startup date for the U.S. side — much later than Enbridge’s last official estimate of the second half of 2020.

Growing demand for energy around the globe is a positive signal for Enbridge but growing opposition to midstream projects like pipelines has increased costs and risks, Monaco told investors.

“It’s tougher to get things done so we’ve had to develop and have developed a unique execution capability and skill set that is built for this environment,” he said.

“In terms of how we grow the business, the approach is that we’re going to focus on projects that optimize and expand the existing footprint, diversifying our opportunity set, again, especially on exports.”

On Monday, Enbridge announced it would work with Enterprise Products Partners L.P. to jointly develop a deep-water offshore crude oil export terminal capable of loading Very Large Crude Carriers (VLCCs) on the U.S. Gulf Coast in Texas.

It also announced that it will advance the development of a new oil storage terminal at Houston with ultimate capacity of up to 15 million barrels of storage and access to crude from throughout North America.

Enbridge announced Monday it would raise its quarterly dividend by nearly 10 per cent to 81 cents per share, effective March 1, up from its previous rate of 73.8 cents.

The shares will have a yield of about 6.3 per cent, based on Enbridge’s closing share price on Monday.

In its outlook for 2020, Enbridge says it expects earnings before interest, taxes, depreciation and amortization of about $13.7 billion.

Distributable cash flow per share for 2020 is expected to be in a range of $4.50 to $4.80 per share.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Out-going Red Deer Food Bank director recalls two decades of providing for a basic human need

Fred Scaife experienced many uplifting moments, along with daily stress

Gathering limits make it a ‘great time to be building a pipeline:’ Alberta minister

EDMONTON — Alberta’s energy minister says it’s a good time to build… Continue reading

Half of Canadians say governments are hiding something about COVID-19: poll

OTTAWA — Half of Canadians believe they’re not getting the whole truth… Continue reading

Scotiabank Q2 profit down from year ago as provisions for credit losses soar

TORONTO — Scotiabank reported a second-quarter profit of $1.32 billion, down sharply… Continue reading

VIDEO: Procession to honour Snowbirds Capt. Jennifer Casey comes to Halifax

Snowbirds service member died in a crash in Kamloops one week ago

Alberta government website has latest COVID-19 statistics

Red Deer Advocate readers can stay up to date on the COVID-19… Continue reading

Political parties don’t need COVID cash

The least essential service throughout the pandemic has been politics — which… Continue reading

Whitecaps ‘keeper Maxime Crepeau dreaming about being back on the soccer pitch

It’s been 80 days since the Vancouver Whitecaps last saw action, so… Continue reading

David Marsden: Jason Kenney is all hat, no cattle

There are few character failings more unappealing than those of people who… Continue reading

Montreal Impact allowed to train individually at Centre Nutrilait

MONTREAL — The Montreal Impact are giving their first-team players access to… Continue reading

Black Crowes, the Trews among artists in Budweiser Stage at Home TV concerts

TORONTO — Live Nation Canada and Budweiser are launching a weekly, one-hour… Continue reading

Sinclair records new version of unreleased Tragically Hip track ‘Get Back Again’

When Gord Sinclair got together last fall with the musicians featured on… Continue reading

Salmon expected to begin arriving soon at Fraser River landslide: DFO

Salmon expected to begin arriving soon at Fraser River landslide: DFO

Most Read