Western Alberta Transmission Line approved

After two years of public hearings, consultations, negotiations and scrutiny, the Western Alberta Transmission Line has been approved.

After two years of public hearings, consultations, negotiations and scrutiny, the Western Alberta Transmission Line has been approved.

The Alberta Utilities Commission approved route and tower options for the $1.5 billion project Thursday. The line will traverse a large section of Central Alberta. The 500 kilovolt line stretches more than 350 km from Genesee, west of Edmonton, to the Langdon area east of Calgary will be built and operated by AltaLink.

“This is the critical backbone in our electrical system,” said Scott Thon, AltaLink president and CEO.

“We have not reinforced it for 30 years and reinforcing it is not only good to ensure reliability for the province, but also it is a key backbone in ensuring we get competition out of the generation sector.”

Thon said a line like this will help power generators get their product to market, making every generator competitive in marketplace.

“It’s about choice,” said Thon. “If Alberta customers have a robust transmission system, then they can get access to the lowest cost producer.”

Jim Law, Alberta Utilities Commission external relations director, said more than 60 per cent of the approved route parallels existing lines. According to a press release the hope is that will minimize the project’s visual and environmental effects and the disturbance of land.

“On portions of the line, which were preferred, many instances there were alternatives developed from landowner suggestions prior to the hearing and throughout the hearing that were then incorporated and then approved,” said Law.

The utilities commission did, however, require two deviations from the preferred route submitted by AltaLink. The AUC has directed AltaLink to the ‘less obtrusive monopole structures’ in the 12-km stretch east of Gleniffer Reservoir. Thon said his company is very experieneced in building those monopoles.

“We use them in a variety of locations and that’s not a concern either,” said Thon.

The other deviation from the preferred route was the Crossfield Tie Option, which Law said was developed in consultation from land owners.

“We were prepared to build the alternative at Crossfield, that’s why we put it forward,” said Thon. “We had a couple options there, the fact the AUC picked the other one is a small adjustment. We’re prepared to build either one.”

The transmission line will cross Hwy 2 just north of Crossfield before continuing on to Langdon.

Public hearings ran for 24 days where numerous residents and land owners expressed their concerns about the line.

But not everyone was pleased with the decision to build the transmission line.

Vittoria Bellissimo, executive director, of the Industrial Power Consumers Association of Alberta, said approval was an “inevitability,” noting the matching Eastern Alberta Transmission Line was approved last month.

“The government decided they wanted these things done, so there you are.”

Bellissimo, whose association represents a coalition of large industries consuming about a third of the province’s power, said the line was approved despite the need for it never being proven by the province.

The massive building project will come at a cost to industrial power users, who are already bracing for an anticipated tripling of power rates over the next six years.

“It’s an unprecedented change in transmission costs,” she said.

It could drive businesses not connected to the oil and gas industry out of the province, she said.

Another industry concern is that all of the attention will be focused on building the power line mega-projects and much-needed regional transmission improvements will drop in priority.

“There’s a bunch of regional projects right now that are needed to connect new consumers to the grid,” she said.

The focus should be on those lines, not the two big transmission lines “that won’t be needed for a number of years if ever.”

AltaLink and ATCO, which is building the eastern line, need to take another look at how they prioritize projects, she said.

“It is difficult to please every interest and the commission’s job was to look at which, if any of what was submitted was the best in terms of being in the public interest from an environmental, social and economic impact perspective,” said Law.

“What the decision does is to look at those impacts and to choose the one that would minimize the landowner, agricultural and environmental impacts.”

Thon said he was pleased the landowners engaged with AltaLink.

“Today that doesn’t stop,” said Thon. “We’re going to be in the field and that’s going to require our teams to continue to talk to those folks and make sure we get it right as we build this line.”

Construction of the transmission line will start early in the new year, with an estimated in-service date in Spring 2015.

Just Posted

Red Deer record store celebrates its last Record Store Day

The Soundhouse, a guitar and record shop in downtown Red Deer, closes its doors next Saturday

WATCH: On 4—20 Day in Red Deer, marijuana users say legal weed a long time coming

Not wanting to wait for the federal government to legalize recreational marijuana,… Continue reading

Former Central Alberta MLA appealing fine for not protecting a list of 20,000 electors

List included names and addresses of voters in Rimbey-Rocky Mountain House-Sundre

Proposed Alberta legislation would protect consumers

Alberta Utilities Commission would be given power to penalize natural gas and electricity providers

Red Deer beginning two major construction projects

Ross Street’s 1935-era water main to be replaced and 67th Street roundabout landscaped

WATCH: Central Alberta bouldering competition

Central Alberta climbers looked to prove they’re the best at a competition… Continue reading

WATCH: Red Deer RCMP and Emergency Services play for Humboldt

Red Deer police officers and firefighters laced up their skates to raise… Continue reading

WATCH: Flooding closes portion of Red Deer’s 43 Street

A portion of 43 Street in Red Deer was closed Saturday morning… Continue reading

After air accidents, survivors grapple with flying again

Hundreds of hands grappling with oxygen masks. Flight attendants warning passengers to… Continue reading

Queen Elizabeth to attend pop concert for 92nd birthday

LONDON — Queen Elizabeth is marking her 92nd birthday with a Saturday… Continue reading

‘Such a great person:’ Funeral being held for assistant coach with Broncos

STRASBOURG, Sask. — Mark Cross was a ferocious competitor when he played… Continue reading

UPDATE: Missing Innisfail woman located

A 54-year-old Innisfail woman, who had not been seen since Wednesday, has… Continue reading

Hellebuyck makes 30 saves, Jets beat Wild in Game 5 to advance to Round 2

WINNIPEG — Bryan Little’s teammates were happy they could deliver something special… Continue reading

Most Read


Five-day delivery plus unlimited digital access for $185 for 260 issues (must live in delivery area to qualify) Unlimited Digital Access 99 cents for the first four weeks and then only $15 per month Five-day delivery plus unlimited digital access for $15 a month